Thursday, 28 March 2013

Following completion of the timber frame, the roof is loaded out with tiles to ensure even weight distribution prior to laying the tiles.  The roofers are making quick work of this, and will be finished early next week following the bank holiday.
 
 
 

Thursday, 21 March 2013

The timber frame is flying up at Rawthorpe Lane with the first roof truss lifted into place by lunchtime on Thursday - timber frame started on Tuesday this week.
 
 

Friday, 8 March 2013

The beam and block flooring works have now been completed and the site is ready for the scaffolding to go up Monday and then the erection of the timber frame the week after.