Friday, 21 June 2013

The subcontractors are pressing on with the internals with the first and second fix of the mechanical and electrical fittings, this allows for the joiners to fit the kitchens.
 
 

Monday, 17 June 2013

The rainwater harvesting tank has been installed this week, it will be used to store rainwater collected from the roofs and then supply this water to the ground floor properties for flushing toilets.
 
 
 

Monday, 3 June 2013

The feeder pillar is installed with ducting fed into the base in preparation for site electric supplies for external lighting, rainwater harvesting and the TV aerials.  It is located in the cycle store and will  be fixed in place when the gravel base and concrete is poured.